Southwest Sandhills WSC is very proud to announce that Water System Improvements consisting of a new 12" distribution line, which will convey water from the existing pump station south to provide additional water to the existing 100,000 gallon elevated storage tank, and a New 300,000 gallon elevated storage tank will begin within the next few weeks. It's finally happening, and no better time than the present ! We'll keep you posted as things get under way.

  • 12" Water Distribution Line
    Estimated Date of Completion: October 16, 2020
  • 300,00 Gallon Elevated Storage Tank
    Estimated Date of Completion: March 20, 2021